General information

Input labelMandatoryDescription
Name     xThe official name of the transportation
Crane capacity     The capacity is the maximal number of Pax which can be transferred with the transportation
Average speed The average speed defines the maximum speed of the transportation (in km/h)
RadiusThe radius is the maximum radius the crane can reach
Type     xThe type defines the kind of transportation. Depending on the type, different input boxes are available
Base     xThe base is the harbour, airport or similar, used as the point of departure on the way to the base or as a base
ID The ID is of unique value to identify the transportation
Work package The transport can be assigned to a certain work package

Current location

Input labelMandatoryDescription

Latitude

     The latitude where the transport is currently stationed
LongitudeThe longitude where the transport is currently stationed

Certificates

Input labelMandatoryDescription
Add certificate List of certificates that can be assigned to the transport, after which you can select the certificate's validity
Certificate groups Automatically assigned, depending on the certificate selected, as certificates can be assigned to certificate groups   

Required skills

Input labelMandatoryDescription
Add required skills Qualification define which single or grouped qualification is necessary for every single technician to enter the transportation

Required skill groups

Input labelMandatoryDescription
Add required skill groups Qualification define which grouped qualification is necessary for every single technician to enter the transportation

Costs

Input labelMandatoryDescription
Day rate The day rate is the price of transportation per day
Fuel costs The fuel costs are the price for every litre of fuel
Mobilisation cost The mobilisation cost is the price per mobilisation

Weather criteria

Input labelMandatoryDescription
Wind speed lifting limit The wind speed lifting limit is the maximal wind for the   

Fuel consumption

Input labelMandatoryDescription
Total fuel consumption per day  The total fuel consumption per day is the averaged sum of fuel consumption per day (litre/day)

Activity durations

Input labelMandatoryDescription
Mobilising time The mobilising time per port visit is the averaged time that the crane needs to prepare in the base before it starts working
Demobilising time The demobilising time per port visit is the averaged time that the cane needs to prepare in the base after finishing the work
Connection timeThe connection time is the averaged time that the transport needs to get out of the usual transit in the position to transfer an employee
Disconnection timeThe disconnection time is the averaged time that the transport needs to get out of the transfer position in the usual transit status

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article